While the excess sales can partially be explained by converting CPU and bitcoin servers, and upgrading functional or burnt out older GPUs, there is finite replaceable powered capacity, in addition to small growth rate of datacenters under active construction that can hope for 2026 opening. “Grey market” diversion to China can be a hidden source of sales.
This is a refined estimate based on taking out networking/software from each of NVidia’s sales channels.
Hyperscalers rarely buy commercial software licenses from NVIDIA (they build their own stacks), while Enterprise buyers are heavily dependent on software subscriptions like NVIDIA AI Enterprise ($4,500/GPU/year). Similarly, networking intensity follows a drastic gradient: a massive LLM training cluster requires a massive networking tax, whereas an Enterprise inference node does not.
To resolve this, we must break down NVIDIA’s $75.2 billion total data center revenue by applying asymmetric networking and software multipliers to each specific customer segment.
Phase 1: Re-Allocating Networking and Software by Segment
NVIDIA’s software layer consists of subscription revenue (which scales with the historical installed base, not just new capacity) and architecture licensing. Its networking segment consists of InfiniBand and Spectrum-X Ethernet switches, adapters, and cables.
Let’s dissect how these costs actually apply to each of the three purchasing categories:
1. Hyperscalers ($38.0B Total Segment)
2. AI Clouds & Sovereigns (~$21.2B of ACIE)
3. Enterprise & Industrial (~$16.0B of ACIE)
Phase 2: Refined Segment-by-Segment Power Calculations
With the refined, asymmetric compute revenue isolated, we can run the physical power conversion using tailored Average Selling Prices (ASPs), system power demands, and facility Power Usage Effectiveness (PUE) metrics.
Category A: Hyperscalers ($29.45B Net Compute)
Product Mix: 50% Blackwell NVL72 / 50% Hopper H200.
Blended Compute ASP: ~$42,000 (reflecting a mix of raw chip pricing and heavy rack-integration premiums).
Total GPUs Shipped:
GPUs=$29,450,000,000$42,000≈701,000 unitsGPUs equals the fraction with numerator $ 29 comma 450 comma 000 comma 000 and denominator $ 42 comma 000 end-fraction is approximately equal to 701 comma 000 units
GPUs=$29,450,000,000$42,000≈701,000 units
Blended Power per GPU: 1,300W (Nominal system draw including Grace CPUs and cooling pumps).
Hyperscaler Grid Footprint (1.15 PUE for ultra-efficient facilities):
Grid Power=(701,000×1,300 W)×1.15≈1.05 GWGrid Power equals open paren 701 comma 000 cross 1 comma 300 W close paren cross 1.15 is approximately equal to 1.05 GW
Grid Power=(701,000×1,300 W)×1.15≈𝟏.𝟎𝟓 GW
Category B: AI Clouds & Sovereigns ($17.38B Net Compute)
Product Mix: 80% Hopper (H100/H200) / 20% standalone Blackwell (B200).
Blended Compute ASP: ~$35,000 (standard market rate for high-end accelerator nodes without bulk hyperscaler discounts).
Total GPUs Shipped:
GPUs=$17,380,000,000$35,000≈497,000 unitsGPUs equals the fraction with numerator $ 17 comma 380 comma 000 comma 000 and denominator $ 35 comma 000 end-fraction is approximately equal to 497 comma 000 units
GPUs=$17,380,000,000$35,000≈497,000 units
Blended Power per GPU: 1,100W (Weighted heavily toward standard Hopper HGX server topologies).
AI Cloud Grid Footprint (1.25 PUE for mixed commercial multi-tenant sites):
Grid Power=(497,000×1,100 W)×1.25≈0.68 GWGrid Power equals open paren 497 comma 000 cross 1 comma 100 W close paren cross 1.25 is approximately equal to 0.68 GW
Grid Power=(497,000×1,100 W)×1.25≈𝟎.𝟔𝟖 GW
Category C: Enterprise & Industrial ($12.00B Net Compute)
Product Mix: 70% low-power inference cards (L40S, H100 NVL) / 30% mainstream H100s.
Blended Compute ASP: ~$18,000 (strongly depressed by high-volume, lower-cost PCIe form factors).
Total GPUs Shipped:
GPUs=$12,000,000,000$18,000≈667,000 unitsGPUs equals the fraction with numerator $ 12 comma 000 comma 000 comma 000 and denominator $ 18 comma 000 end-fraction is approximately equal to 667 comma 000 units
GPUs=$12,000,000,000$18,000≈667,000 units
Blended Power per GPU: 450W (Reflecting the dramatically lower power draw of enterprise edge and inference cards).
Enterprise Grid Footprint (1.25 PUE for on-premises or traditional enterprise cages):
Grid Power=(667,000×450 W)×1.25≈0.38 GWGrid Power equals open paren 667 comma 000 cross 450 W close paren cross 1.25 is approximately equal to 0.38 GW
Grid Power=(667,000×450 W)×1.25≈𝟎.𝟑𝟖 GW
Phase 3: Final Comparison: GW Sold vs. GW Deployed
Now, let’s look at how this highly refined model maps against the 1.55 GW of net-new trackable data center capacity that physically came online across the globe during the quarter:
| Customer Segment | NVIDIA GW Sold (Refined Power Footprint) | Actual New GW Deployed (Capacity Online) | Net Capacity Gap (Deficit) |
|---|---|---|---|
| Hyperscalers | 1.05 GW | 0.93 GW | +0.12 GW (120 MW Deficit) |
| AI Clouds & Sovereigns | 0.68 GW | 0.42 GW | +0.26 GW (260 MW Deficit) |
| Enterprise & Industrial | 0.38 GW | 0.20 GW (Est. legacy footprint) | +0.18 GW (180 MW Deficit) |
| Total Global Market | 2.11 GW | 1.55 GW | +0.56 GW (560 MW Deficit) |
Key Takeaways from the Refined Model
This model confirms that the “homeless GPU” crisis is primarily concentrated outside of the core hyperscalers, driving smaller AI clouds to aggressively bid up any available third-party power capacity in the market today.

This is the official technology community of Lemmy.ml for all news related to creation and use of technology, and to facilitate civil, meaningful discussion around it.
Ask in DM before posting product reviews or ads. All such posts otherwise are subject to removal.
Rules:
1: All Lemmy rules apply
2: Do not post low effort posts
3: NEVER post naziped*gore stuff
4: Always post article URLs or their archived version URLs as sources, NOT screenshots. Help the blind users.
5: personal rants of Big Tech CEOs like Elon Musk are unwelcome (does not include posts about their companies affecting wide range of people)
6: no advertisement posts unless verified as legitimate and non-exploitative/non-consumerist
7: crypto related posts, unless essential, are disallowed
The surplus sales are actually heavily underestimated because the datacenter capacity additions for 2025/26 include non Nvidia hardware. It “appears” that under half of their sales actually make it into datacenter capacity additions.
1. Stripping Non-NVIDIA Slices from the Available GW Grid
To see the true depth of the backlog, we have to look at how much of that newly brought-online data center capacity was immediately consumed by alternative architectures during the 2025 calendar year (4.10 GW total online) and Q1 2026 (1.55 GW total online).
A. The Hyperscaler Internal Custom Silicon Tax (ASICs)
The largest tech giants do not deploy NVIDIA exclusively. They heavily prioritized their own lower-cost, custom-tailored accelerator chips to handle their native workloads:
B. The AMD Alternative Squeeze
AMD’s MI300X and MI325X series secured massive enterprise and cloud traction, specifically anchoring flagship clusters inside Microsoft Azure and Oracle Cloud Infrastructure (OCI). AMD’s total shipment footprint accounted for roughly 400 MW of power demand globally over this timeframe.
C. Specialized Wafer-Scale Architectures (Cerebras)
While smaller in pure megawatt terms compared to hyperscalers, Cerebras built massive high-density footprints. Their multi-million dollar wins—such as the massive 750 MW master deployment framework with OpenAI—began systematically occupying high-density colocation space. Across 2025 and Q1 2026, Cerebras deployments locked down roughly 100 MW of specialized, high-cooling capacity.
2. Recalculating the True NVIDIA “Space Deficit”
When we subtract these non-NVIDIA hardware deployments from the total physical data center capacity brought online, we find the Net Grid Space Actually Available for NVIDIA:
Now, let’s remap this accurate “Available Space” baseline against the True Grid Power Shipped by NVIDIA (GW Sold) that we calculated using our refined financial models:
The Compounding Backlog Realities
Only 2.15gw (out of 5gw) of global datacenters under active construction with hope for 2026 completion is for Nvidia hardware. If there is already high excess inventory (not guaranteed as result of hand me down GPU replacement) then sales/growth must hit a wall eventually. Next 9 months of optimistic deployments is more than next quarters sales forecast.
Yet another big problem for Nvidia is that the H200 is their better product for FP8 mainstream LLM service. Vera-Rubin only has 30% more performance per watt, gb200/300 is lower performance/watt at fp8. But the big expense of all its later generations is liquid cooling, and the extreme weight of liquid cooled racks/NVL72 (3000lbs) that require ultra strong floors with embedded pipes inside them. In yet another F’d up supply chain crisis driven by AI is a 2 year backlog for liquid cooling equipment.